BINH KHANH RESETTLEMENT RESIDENTAL AREA
The project area is 60.678m2. The project includes the following facilities:
– 5-floors cultural center on 5.793m2 with 40% construction density, is 16m from Mai Chi Tho Route.
– 5-floors medical station on 2.660m2 with 40% construction density, slab area is 5.850m2.
-4-floors Primary school, secondary school, high school on 23.032m2, slab area is 41.500m2
-3-levels kindergarten on 8.107m2, slab area is 11.350m2.
-Commercial building on 21.086m2 with 3 blocks, the maximum level is equal to 5 floors.
-Park, sport center & channels on 64.162m2.
Foreign trade investment & construction corporation was selected to be the main contractor of Complex 1 in the 6220-apartments projects with 2200 apartments.
The project started in July 2014 and delivered in Quarter II, 2016.
Location | BINH KHANH WARD, DISTRICT 2, HO CHI MINH CITY |
Client | THUAN VIET CONSTRUCTION & INVESTMENT COMPANY |
Tender package | SUPERSTRUCTURE & FINISHING WORK |
Scale | 2,220 RESETTLEMENT APARTMENTS (AREA 1) |
Contract value | 407 BILLIONS VND |
Schedule | 2013 - 2016 |